Going for Gold on the Takitimu North Link

Source: New Zealand Transport Agency

Autumn is a time to celebrate the harvest at the Takitimu North Link Stage 1 project, following a golden construction season.

With piling on the project now 96 percent complete, the highway is really on solid ground,” says Manager of Infrastructure Delivery, Darryl Coalter.

“Interest in the project is extremely high with 370 people turning up to meet the team and see the progress at our Open Day recently, followed by a visit by the Minister of Transport, Chris Bishop, who declared the project ‘amazing’ and said he couldn’t wait to see it open.

“With 11 culverts now complete (out of 19), 72 percent of the utility work finished and over 163,000 hours of machinery work under our belt, we’re heading into the winter months in a strong position to continue to build our structures,” says Mr Coalter.

There are 6 bridges currently in construction, so while earthworks wind down for the cooler months, the site will still be a hive of activity, keeping the 275 people working on the project very busy.

“We’ve commenced trials for the first section of pavements at Te Mete, and we’ve already got 2km of drainage in, so it’s all happening both above the ground and below.

“And as the seasons turn, the 2025 planting season will see 164,000 plants go in the ground, adding to the 70,000 already in, so there’s heaps to look forward to.”

But don’t just take Mr Coalter or Mr Bishop’s word for how epic things are looking – check out the progress on this fly through video:

Watch video on Youtube(external link)

Piling on 15th Avenue.

Minden interchange towards WETI.

Fast facts

  • 275 people currently working on the project
  • More than 2478 people inducted and worked on various aspects of the project to date
  • Over 22.5 million hours worked since project started
  • 90 subcontractor staff engaged, with half of those local businesses
  • 4 bridges built 6 under construction
  • 2.3 million cubic metres of dirt moved (of total 3 million cubes)
  • 8.84km of piles on the project, 96 percent complete
  • 800,000 linear metres of wick drains installed, to reduce settlement time
  • 70,000 plants in the ground, of more than 900,000 required in total
  • 11 out of 19 culverts completed
  • 2km of network drainage installed out of 13km
  • 72 percent complete of utility work (includes Power, Gas, Fibre, Telecommunications, Water, Sewer)
  • Total machine hours 163,149 (up until end of March 2025)
  • 35 dump trucks, 10 bulldozers and 20 excavators on site
  • Commenced first section of pavement trials at Te Mete.

Construction to start on new average speed safety cameras in Auckland

Source: New Zealand Transport Agency

New Zealand Transport Agency Waka Kotahi (NZTA) will begin construction of a new pair of average speed safety cameras to improve safety on Pine Valley Road, in Dairy Flat Auckland, from next week.

NZTA Auckland and Northland Director of Regional Relationships, Steve Mutton, says the safety cameras aim to significantly reduce the number of people traveling over the speed limit on this road and lessen the likelihood of a serious or fatal crash.

“The types of crashes that happen and are likely to happen on this stretch of road, the volume of traffic, and driver behaviour all tell us that there is a serious risk of people being killed or seriously injured in crashes on Pine Valley Road. We also know that risk can be significantly reduced if more people drive to the speed limit. By installing safety cameras here we can encourage just that.

“In June 2024 we ran a speed survey on this stretch of road that showed around 74 percent of drivers were speeding. Despite the 80 km/h speed limit, the average speed vehicles were travelling was almost 90 km/h. 

“There were three crashes between 2018 and 2023 that resulted in people receiving serious, and potentially life changing, injuries.”

One camera will be installed near the Kahikatea Flat Road intersection and the other near the Pine Valley Road roundabout. 

When installed, the two cameras will work together, measuring the average speed drivers travel between them. Drivers will only be ticketed if their average travel speed over the entire distance between the two cameras is over the limit – they aren’t ‘pinged’ by a single camera or at a single point where they are over the speed limit.

“We know that average speed safety cameras are more effective at reducing deaths and serious injuries than the traditional speed cameras we’ve had in New Zealand. We expect they will reduce deaths and serious injuries by around 48 percent,” says Mr Mutton.

“Safety cameras will reduce speeding, ensuring that if crashes do happen, the people involved are far more likely to walk away unharmed.” 

Initial construction works will include installing an underground power supply, completing foundation works and installing a metal barrier that will protect maintenance workers and any vehicle that leaves the road in a crash.  

The poles and cameras will not be installed until later this year. Before the cameras begin operating ‘Average speed camera area’ signs will be installed, giving drivers a reminder to check their speed and slow down if needed.

NZTA is expecting to begin operating its first average speed safety cameras at Matakana Road, Warkworth, later this year, and will progressively bring other average speed safety cameras online in the following months. 

Find out more about NZTA’s safety camera work.

Falling leaves much softer than falling rocks

Source: New Zealand Transport Agency

With the leaves falling in Central Otago and Queenstown Lakes Districts, the autumn rockfall scaling programme at the Nevis Bluff, on SH6 between Cromwell and Queenstown, will get underway shortly, says NZ Transport Agency Waka Kotahi (NZTA).

The rock scaling occurs every autumn and spring with abseilers, suspended on ropes, inspecting the rocky face and removing loosened rocks that are hazardous to highway users many metres below.

Sensor installation on Arch Column, part of the Nevis Bluff, spring of 2024.

Wayo Carson, one of the most experienced rock scalers working on the Nevis Bluff, doing an extensometer measurement in 2021 (An extensometer provides an accurate measuring tape in millimetres to 4 decimal places).

“People should be ready for delays up to about ten minutes and allow some extra travel time for journeys between Cromwell and Queenstown,” says Peter Standring, NZTA Maintenance and Contract Manager in Central Otago.

The work is scheduled to take place over three weeks from Monday, 5 May, through to Friday, 23 May, 8 am to 5 pm weekdays, subject to weather conditions.

“We know these delays can be frustrating, but we’re asking people to be patient and to understand that they are necessary to ensure their safety, which is our number one concern,” says Mr Standring.

Abseilers working over the rocky schist faces aim to release rock, loosened by the ongoing erosion, in a controlled way when there is no traffic on the highway.

This work is part of NZTA’s ongoing monitoring and management programme for the Nevis Bluff, which is continuously monitoring movement and changes on the geologically complex bluff.

The Nevis Bluff is about half-way between Cromwell and Queenstown – 25 minutes from Cromwell, 35 minutes from Queenstown.

Work on the cycle trail, currently under construction, will be paused for a few days while the abseilers are overhead.

NZTA thanks everyone for their patience and for taking care while this important safety work is completed leading into the busy winter period.

Piece of WWII history uncovered on Te Ara Tūtohu: SH3 Waitara to Bell Block

Source: New Zealand Transport Agency

A piece of Taranaki’s Second World War history has recently been uncovered during work on Te Ara Tūtohu: SH3 Waitara to Bell Block.

Two Home Guard rifle pits were found to the north of the intersection of State Highway 3 (SH3) and De Havilland Drive in Bell Block.

It’s likely they were constructed between 1941 and 1942 as a defensive position to protect the Bell Block Aerodrome on Te Arei Road, which was being used as a Royal New Zealand Air Force training base, from a potential invasion by Japanese forces.

The Home Guard was formed in 1940 in response to the potential threat posed by the Empire of Japan during the Second World War. Membership was initially voluntary but became compulsory from 1942 for men aged 35-50.

Home Guard – Te Ara Encyclopedia of New Zealand(external link)

“These are textbook Home Guard pits,” says project archaeologist Daniel McCurdy. “These are so textbook, that in fact one of them conforms exactly (within a few inches) to the standard set out for the Home Guard. However, instead of an optional drainage trench at the base, the men chose to place timbers instead, likely reclaimed from the local farm.”

There have been a number of archaeological finds on Te Ara Tūtohu since physical works began in 2023. The project works closely with archaeologists and cultural monitors in these instances. Depending on what is found, the find may be removed or documented and left in place.

“The area we are working in is historically significant. It’s important that whenever we come across a potential archaeological find in the course of our work that we take the time necessary to investigate,” says Te Ara Tūtohu project manager Calvin Rorke.

“I know that I, and many of us working on Te Ara Tūtohu, have learnt a lot about the history of this area through our work on the project.”

Te Ara Tūtohu: Waitara to Bell Block project

Night closures coming for State Highway 2 – Masterton to Carterton

Source: New Zealand Transport Agency

Late April and early May will see maintenance works underway on State Highway 2 between Masterton and Carterton.

Roxanne Hilliard, Wellington Alliance Manager, says contractors will complete a wide range of maintenance tasks.

“They will be fixing safety barriers – we have four recent barrier strikes that need to be fixed. It is critical damaged barriers are fixed as they are instrumental in preventing head on collisions.

“They will also be doing line marking and carrying out water cutting – this removes excess bitumen from the road surface, improves road grip, and makes it safer to drive on,” Ms Hilliard says.

Ms Hilliard says the work requires road closures over five consecutive nights, and State Highway 2 will be closed to traffic in both directions.

“We appreciate full closures do affect drivers. However, with winter approaching it is vital this section of the highway is in the best shape it can be for the winter months ahead.”

The work will be underway from Sunday, 27 April to Thursday, 1 May. The highway will be closed to north and southbound traffic each night between 9 pm and 4 am (works conclude Friday, 2 May at 4 am).

Ms Hilliard says local road detours will be available via Chester and Norfolk Road, and Cornwall Road and Hughes Line (see work and detour details below).

“Because these are local roads, road users must drive to the conditions, obey the speed limit, and be patient if there is queued traffic. We want people to get to their destinations safely.”

Drivers travelling through Wairarapa also need to be aware of other road works on State Highway 2 that will affect their journeys. This includes road rebuild work in Greytown and drainage works in Masterton.

It is essential people plan ahead and allow extra time for their journeys.

NZTA/Waka Kotahi and the Wellington Transport Alliance thank the public for their patience and cooperation while these essential state highway maintenance works are completed.

Works schedule and detour routes

  • Sunday, 27 April to Thursday 1 May. 9 pm – 4 am
  • State Highway CLOSED in both directions between Chester and Norfolk Roads
  • Sunday and Monday nights (27 and 28 April):
    • Northbound traffic detour via Chester and Norfolk Roads
    • Southbound traffic detour via Cornwall Road and Hughes Line
  • Tuesday, Wednesday, and Thursday nights (29 April – 1 May):
    • All traffic must detour via Hughes Line and Cornwall Road.

View larger night closures map [PDF, 365 KB]

More information

Next steps for state highway speed reversals programme

Source: New Zealand Transport Agency

Community consultation has concluded, results have been analysed, and decisions have been made on speed limits for 49 state highway corridors, with most locations set to return to their previous higher speed limits.

On 29 January 2025, the Minister of Transport confirmed that 38 sections of state highway were subject to speed limit auto-reversal under the Setting of Speed Limits Rule 2024, with a further 49 sections open to community consultation to confirm whether there was public support to retain current lower speed limits. 

Setting of Speed Limits Rule 2024

NZ Transport Agency Waka Kotahi (NZTA) carried out six weeks of public consultation on these 49 sections of state highway between 30 January and 13 March, and the NZTA Board considered the consultation results earlier this month.

Over 21,500 people had their say, and based on their feedback, 43 locations will return to their previous higher speed limits, with six remaining at their current lower speed limits.

The six locations that demonstrated majority public support, as required by the Setting of Speed Limits Rule 2024, to keep their current lower speed limit were: 

  • SH30 Rotorua South  
  • SH5 Waipā State Mill Road 
  • SH5 Waiotapu, 
  • SH3 Whanganui 
  • SH3 Palmerston Northeast to Whakarongo
  • SH94 Homer Tunnel to Milford Sound.  

Local road users and communities in these six locations made their support for the current lower speed limits clear through consultation feedback:

  • More than 50 per cent of respondents asked for the current lower speed limits to be retained for each of these locations. NZTA can now confirm that these lower speed limits will remain in place.  
  • Public support levels for the other 43 sections of state highway did not reach a similar level of support, with less than 50 per cent of respondents wishing to retain lower speed limits. 
  • NZTA will now add these 43 locations to its wider list of speed limit reversals and will begin notifying local communities in each of the locations about upcoming signage changes.

Implementation of the speed limit reversals will be rolled out in monthly tranches, with all reversals to be in effect by 1 July 2025, as required by the Setting of Speed Limits Rule 2024. 

NZTA acknowledges there are a wide range of opinions on speed limits, and thanks everyone who took the time to share their views.  A summary of feedback received through the consultation process is available here:

Consultation summary report – Speed reversals [PDF, 1.9 MB]

This feedback will be valuable in shaping future speed reviews. This includes concerns voiced by local schools and marae. 

NZTA will now work with those schools and iwi, hapū, and marae to see what other safety interventions, such as Variable Speed Limits (VSLs), can be applied under the Rule to help them keep vulnerable users safe. 

VSLs are required by the Rule to be implemented outside all schools by 1 July 2026. 

Work is continuing separately on consultation on 16 of the 38 sections of state highways subject to auto-reversal requirements under the Rule, but where local communities have given strong feedback that they want to keep lower speeds.  
 
For consultation on these 16 sections of state highway, NZTA is required to follow different process under the Rule. This involves undertaking a full speed review, which includes looking at technical, safety, cost and economic data, alongside consultation feedback, before being able to confirm final speed limit outcomes.

Consultation on these 16 sections of state highway is open for six weeks, between 2 April and 14 May, and the results of this phase of work will be known in June.  

If the new speed reviews determine a lower speed should be confirmed, instead of the higher one set through the reversal process, this change will take place immediately after 1 July 2025.

More information about the sections of state highway currently under consultation can be found on the NZTA website:  

New consultation on urban connectors 

More details on the sections of state highway reversing to their previous higher limits is also available on the NZTA website can be found here: 

Speed reversals and consultation – transitional changes in 2024-25

Notes to editors:  

  • The new Setting of Speed Limits Rule (the Rule) requires that a range of specified roads managed by NZTA and local council road controlling authorities (RCAs), where speed have been lowered since January 2020, must automatically reverse back to their previous higher speeds by 1 July 2025. 
  • While NZTA has published a list of 89 road locations on state highways that are required to reverse, the Rule also allowed for the agency to consult on some state highways in two of the five categories (rural connectors and inter-regional connectors), before confirming its final list for implementation. 
  • There are five categories of specified roads required to auto-reverse under the Section 11 Transitional provisions of the Rule. These categories are managed by both local government and NZTA. NZTA was the only road controlling authority (RCA) able to consult on retaining current lower speed limits on some state highways as part of these provisions in two of the five categories – rural connectors and interregionals.   
  • All RCAs must confirm their lists to reverse to the Director of Land Transport in May 2025, for uploading to the National Speed Limits Register (NSLR). Implementation is required to take place by 1 July 2025.   
  • An additional 16 locations included in NZTA’s list of specified roads are now going through full new speed reviews under different provisions of the rule. If the new speed reviews determine a lower speed should be confirmed instead of the higher one set through the reversal process, this change will take place immediately after 1 July 2025. The results of these speed reviews will be known in June 2025. 

The road ahead: Northland Corridor Sections 2 and 3 taking shape

Source: New Zealand Transport Agency

NZ Transport Agency Waka Kotahi (NZTA) is progressing design investigations within the emerging preferred corridor for Section 2 and Section 3 of the Northland Corridor Roads of National Significance project announced by Transport Minister, Hon. Chris Bishop earlier today.

The emerging preferred corridor for the 45km section between Te Hana and Port Marsden Highway (Section 2) and the 26km section between Port Marsden Highway and Whangārei (Section 3) allow further work to get underway to deliver benefits faster for Northland communities and businesses. 

The individual sections within the emerging preferred corridor are: 

Section 2: Te Hana to Port Marsden Highway  

  • Section 2A: A new route to the east of SH1 between Te Hana and Brynderwyn Hills​ 
  • Section 2B: A new route to the near east of SH1 at the Brynderwyn Hills​ 
  • Section 2C: A new route to the west of SH1 between Brynderwyn Hills and Port Marsden​ Highway 

Section 3: Port Marsden Highway to Whangārei  

  • Section 3A: A new road near to SH1 between Port Marsden Highway and SH15 Loop Road
  • ​Section 3B: A widened existing SH1 corridor approaching urban Whangārei  

NZTA Northland Corridor Programme Director, Derek Robertson, says NZTA is working at pace to deliver a safer, more resilient and more efficient road for Northland.

“The Northland Corridor will address the critical resilience and safety issues facing the current road.”  

Mr Robertson acknowledges that while this is a very exciting time for Northland, it’s an uncertain time for landowners in the emerging preferred corridor area. 

“Now that we have identified the emerging preferred corridor, we will start contacting potentially impacted landowners who are within the area to let them know the next steps. Due to the size of the project, this will take time, but we are working hard to contact landowners as quickly as we can.  

“The emerging preferred corridor is a larger area than will be required for the final route. Within the emerging preferred corridor there are still several different places the road may go.    

“The next piece of work we do will be to refine this route further so we understand more about where the final road will go, and the land that may be required for it.  

“We expect to narrow down the emerging preferred corridor to the preferred route for NZTA Board for endorsement in August/September this year. After that we will be able to confirm the preferred route and provide landowners with greater certainty about any impacts to their properties.” 

Alongside this, NZTA is continuing work on Section 1 Ara Tūhono – Warkworth to Te Hana. The procurement process got underway last month and detailed design and construction for this section is expected to begin at the end of next year. A completion date for Ara Tūhono – Warkworth to Te Hana will be confirmed following procurement but is currently expected to be around 2034. 

“The Northland Corridor will be a vital link between Northland and Auckland, unlocking economic growth and productivity, and allowing people and freight to move efficiently, quickly and safely across the region. It will bring the resilience Northland needs to thrive after years of significant road closures due to severe weather events,” Mr Robertson says.

For more information about the Northland Corridor, please visit:

Northland Corridor

Brynderwyn Hills recovery work proves its worth during Cyclone Tam

Source: New Zealand Transport Agency

Temporary speed restrictions will remain in place at the site of a slip on State Highway 1 Brynderwyn Hills.

The slip on State Highway 1 Brynderwyn Hills on Sunday (20 April 2025).

NZ Transport Agency Waka Kotahi (NZTA) says the slip reduced traffic to a single lane for a short, 3-4 hour period on Sunday evening before the road was reinstated to 2 lanes with a temporary speed restriction still in place.

SH1 Brynderwyn Hills suffered significant damage from severe weather events in early 2023, resulting in severe underslips and overslips. A range of recovery and enabling works were then carried out, finishing last year, to help the road better withstand future weather events.

The work, which included soil nailing, mesh, drainage improvements and benching (levels cut into the hillside), reduces the likelihood of overslips by contributing to a more stable hillside.  The wider road shoulder also provides space to clear any slips with less disruption to traffic, in the event one does occur.

Auckland and Northland Regional Manager Maintenance and Operations, Jacqui Hori-Hoult, says the slip highlighted the effectiveness of recent recovery works by minimising disruption to traffic.

“Keeping this key route open during severe weather events, like Cyclone Tam, was exactly what the recently completed recovery work was designed for.

“The benches caught falling trees and debris, preventing the majority of the slip from reaching the road, avoiding a full highway closure and ensuring we were able to maintain access for road users at all times across the busy Easter holiday weekend.”

Crews will continue to monitor the slip and work to remove the trees and debris on the benches above the highway will take place on Thursday, ahead of the long weekend.

Delays due to the temporary speed restrictions were minimal, even with an increase in traffic due to the holidays.

“We appreciate everyone’s patience as our crews worked hard across the weekend to keep traffic moving safely and efficiently across the region.”

Longer-term, a Brynderwyn Hills alternative will be part of the Te Hana to Port Marsden section of the Northland Corridor, made up of 3 Roads of National Significance (RoNS).

For more information about the resilience work, please visit:

SH1 Brynderwyn Hills | NZ Transport Agency Waka Kotahi

For more information about the Northland Corridor, including Section 2 Te Hana to Port Marsden, which includes a Brynderwyn Hills alternative, please visit:

Northland Corridor | NZ Transport Agency Waka Kotahi

Soil and trees are caught on the benches above the state highway to stop them reaching the road.

No more tomo fomo on State Highway 4

Source: New Zealand Transport Agency

State Highway 4 (SH4) between Manunui and National Park has reopened early to 1 lane this afternoon under stop/go, and will be fully reopen by the end of the day under a temporary speed limit.

The highway has been closed since Monday morning 14 April for emergency repairs, due to the discovery of a tomo (cavity) under the road at Mansons Siding, Raurimu.

“The tomo was likely formed due to erosion from a concentration of moisture under the road,” says Sandra King, System Manager Waikato for NZ Transport Agency Waka Kotahi (NZTA).

“Repairs involved excavating 5 metres below the road level. The team constructed a drainage blanket at the base of the excavation and again at approximately 2 metres deep to ensure any moisture in this sensitive geological location was able to drain.

“Contractors finished building material back up to 400mm below surface this morning and are reinstating the pavement now,” Ms King says.

The speed limit will remain over the Easter weekend to allow the surface to settle safely before contractors return next week to prep the surface and seal.

Ms King advises road users to take care through the site and thanks them for their patience.

A Downer contractor using a remote controlled mini padfoot trench roller.

Cyclone Tam makes for challenging driving

Source: New Zealand Transport Agency

With severe weather arriving ahead of the busy Easter holiday period, NZ Transport Agency Waka Kotahi (NZTA) is advising road users in the Waikato and Bay of Plenty, to be prepared and take extra care on the roads.

Heavy rain and strong winds are forecast, with MetService issuing a severe weather warning from tonight until end of day on Friday 18 April for Coromandel and Western Bay of Plenty.

The orange warning is likely to be extended further into the Waikato and across the Kaimai Range.

With school holidays, and Easter approaching, it’s busier than usual on our roads, and Waikato Journey Manger for NZTA, Andrew Brosnan, urges motorists to be vigilant.

“Essentially, the message is –  be ready for difficult driving conditions. There’s the potential for surface flooding and slips. Anticipate that there could be trees or debris on the road just around the next corner. There’s also a risk of downed powerlines – so expect the unexpected.

“If you need to travel, allow extra time for your journey. Slow down and keep a safe following distance from the vehicle in front. Keep your headlights on to increase visibility.

“Thunderstorms are possible on Friday. While the current estimate is up to 250 mm of rain to fall on the Comomandel Ranges, there is potential for this to increase.

“Be aware that streams and rivers may rise rapidly. Strong winds are creating dangerous coastal conditions around the upper North Island, with large waves potentially causing coastal inundation and erosion. The highest risk for the Coromandel is around high tide.”

NZTA contractors are out clearing critical drainage areas on the network and have crews on standby to manage any issues as the weather takes hold.

Road uses should be aware that there may be some areas of the network where traffic management or temporary speed limits are in place. There will be traffic management in place on State Highway 25 at the Pepe Steam Bridge at Tairua over both Easter and Anzac weekends, to help keep traffic moving over the holiday period.

“Please adhere to temporary speed limits and follow the directions of traffic management in work zones, even if you can’t see active work underway. It is there for your protection, the protection of workers and other motorists. This is especially important in poor weather,” Mr Brosnan says.

Plan ahead before you travel with the Easter and Anzac travel advisory in the NZTA Journey Planner.

Easter and Anzac holiday weekends 2025 | NZTA Journey Planner(external link)